BedZED: Construction Materials Report. Contents:

Material selection (examples)

Example case studies

This chapter describes the main components that make up a ZED building and the reason for each material choice. Numbers in boxed brackets indicate a case study number, eg [6]. More details on that material can be found in its case study in chapter 6.

Chapter 5 gave an overview of all the materials used at BedZED. This chapter 6 provides details of some of the more unusual materials. It compares the BedZED material with conventional alternatives and describes design, quality and sourcing issues, contractual arrangements and cost implications. Each of the 15 case studies quantifies the environmental impact of the material and compares with the conventional choice. The case studies are graded according to:
• How easy it was to acheive..
• Cost-effectiveness.
• The significance of the environmental benefits.

All gradings are relative to the conventional material choice for that purpose.

The Case Studies included in the complete report
are: (linked examples are in blue)

1 LOCAL TIMBER 6 KITCHEN FITTINGS
_ Oak weatherboarding 7 RECLAIMED DOORS
_ Ash floor boards 8 RECLAIMED STEEL
2 RECLAIMED TIMBER 9 RECLAIMED PAVING SLABS
_ Internal studwork 10 CONCRETE FLOOR SLABS
_ External studwork 11 RECYCLED AGGREGATE
_ Bollards 12 RECYCLED SAND
_ Floor boards 13 LOCAL CONCRETE BLOCKS
3 FSC CERTIFIED TIMBER 14 LOCAL BRICKS
4 PLYWOOD 15 INSULATION
5 WINDOW FRAMES  

 

case study 5: window frames

The BedZED Design Team sought to avoid high impact materials such as uPVC and aluminium. So when it came to selecting window frames, timber was the obvious choice.

Options explored

The Design Team explored the best environmental option -frames made from locally sourced hardwood. This long life and low maintenance material has lower life cycle costs than softwood alternatives which would require a £14,000/year maintenance programme and more frequent replacement. Using a locally distinctive product adds character to a development; whilst creating a demand for locally grown timber products brings neglected UK woodlands into economically viable management.

However, local joinery companies were reluctant to work with local chestnut, when their experience lay in producing softwood frames. There was little local expertise in manufacturing high performance, triple glazed, airtight windows. Also, the scale of the contract was too large for the companies operating locally. These factors led to prohibitively high quotes.
The geographical net had to be spread wider. Danish window specialist Rationel were able to meet both stringent performance demands and cost criteria. Rationel source 40% of their timber from FSC certified sources.

Cost comparison

Timber windows are typically cheaper than aluminium or uPVC but can attract higher maintenance costs. The Rationel windows on BedZED are high specification in terms of air tightness, thermal performance and also durability. Their costs are higher than most timber windows but maintenance costs are lower.

The supply cost of Rationel windows on BedZED (excluding installation) for double and triple glazed ranged between £130/m 2 and £300/m 2 . Equivalent aluminium frame windows from Alcoplan ranged from £185/m 2 to £275/m 2 . uPVC windows from Ankers & Sons in the same price range only achieved U-values of 1.9W/m 2 , as compared with 1.0-1.6W/m 2 for Rationel's timber windows.

Quantified environmental benefits

BRE have compared the BedZED softwood timber framed windows from Denmark with the conventional choice of uPVC windows manufactured in the UK and with aluminium framed windows (all double glazed).
BRE are aware that better quality LCA data on uPVC is now available and they are hoping to work with the British Plastics Federation in the near future to update this data.

Saving from using BedZED Specification

  uPVC windows Aluminium windows
Ecopoints 4,800 4,500
Embodied CO2 (kg 100 yr eq) 793,900 838,000
Embodied Energy (GJ) 12,000 9,750
Eco-footprint (ha years) 176 186

case study 8: reclaimed steel

98 tonnes of reclaimed structural steel has been used on BedZED. This amounts to 95% of the structural steel on the scheme and is mainly used in the steel frames in the workspaces. The sections are retrieved from demolition sites within the 35 mile radius.

Design

The engineers specified a range of section sizes that could be used for each piece. Connection details were designed to accommodate this range of sizes. This approach, at an early design stage, allowed for flexibility in sourcing the reclaimed sections.
Once reclaimed steel sections had been identified, The Historic Sections Book was used to obtain allowable stresses.

Quality

The engineers specified a range of section sizes that could be used for each piece. Connection details were designed to accommodate this range of sizes. This approach, at an early design stage, allowed for flexibility in sourcing the reclaimed sections.
Once reclaimed steel sections had been identified, The Historic Sections Book was used to obtain allowable stresses.

Reclamation process

Sand blasting, fabrication and painting of all new and reclaimed structural steel took place in the steelwork contractor's workshop. The reclaimed steel required an extra pass through the sand blaster and treatment with a zinc-rich coating.

Curved steel sections

It was not possible to use reclaimed steel for the curved sections on BedZED. The local section bender was unwilling to pass reclaimed steel through their machine. Due to time and programme pressures, the contractors proceeded with new steel for these pieces rather than finding an alternative company. There is no technical reason why reclaimed steel should not be curved on future projects.

Cost comparison

On BedZED, using reclaimed steel was 4% cheaper than using new. The cost average was £300/tonne, although this price varied considerably according to the source. The comparative tender price for new steel was £313/tonne.
The cost of additional staff time in sourcing reclaimed steel and the visual inspection has been estimated at £1,000, making the use of reclaimed steel effectively cost neutral.

Construction contract

The steelwork package was tendered competitively on the basis of new steel. Tenderers were then asked for a rate reduction for the free issue of reclaimed steel. Cut off dates for the placements of orders for new steel were agreed and responsibility for sourcing and delivering the reclaimed steel was with the construction managers.

Sourcing / Availability

There are not vast quantities of good quality reclaimed structural steel stored in reclamation yards. It requires active searching and probably some luck to find the right materials. For this reason, it is important to build in as much flexibility as possible and to allow for long lead times.
In the absence of sourcing from a yard, the ideal situation is to identify a steel source in a building that is about to be demolished and to have it extracted carefully.

Risk allocation

The Construction Manager purchased the reclaimed steel on behalf of the Client. There was a risk to the Client as with any free-issue materials. The structural engineer, Ellis & Moore held the risk associated with the structural integrity of the steel.

Quantified environmental benefits

BRE have compared the impacts of the recalaimed steel with new. They have allowed for one additional grit blasting prior to use. Overspecification of the reclaimed beams was very small (<0.5%), as most of the reclaimed beams were in good condition, and were standard sizes. The environmental impacts of new steel are based on the typical mix of steel sections manufactured from virgin (BOF) and recycled (EAF) steel consumed in the UK.

Ecopoints 1,000
Embodied CO2 (kg 100 yr eq) 81,500
Embodied Energy (GJ) 2,580
Eco-footprint (ha years) 137

These savings reduce BedZED's total eco-footprint by approximately 3.8%.

In addition

The Construction Manager purchased the reclaimed steel on behalf of the Client. There was a risk to the Client as with any free-issue materials. The structural engineer, Ellis & Moore held the risk associated with the structural integrity of the steel.

As a spin off from BedZED, 11.5 tonnes of reclaimed structural steel was also used on the entrance building to the Earth Centre, resulting in 303GJ embodied energy savings, 21 tonnes of CO2 saved and an eco-footprint reduction of 12.6 hectares.
reclaimed steel v new steel

case study 8: recycled sand

BedZED used 279 tonnes of recycled crushed green glass. It was used in the hard landscaping as bed-ding for paving slabs and replaced the same quantity of virgin sand.

Procurement

The recycled product was bought direct from Day Aggregates by the groundworks contractor, Edenway Contractors Ltd. It is an off-the-shelf product. Product Datasheets are available from Day.

Aggregates

Edenway is now suggesting this product to other Clients and using it whenever possible. They experienced no difficulties in obtaining or using this product and it brings them a cost saving. Day Aggregates say that sales have increased since the introduction of the Aggregates Tax in April 2002.

Safety

Risk assessments and COSSH statements were prepared by the suppliers. The finely ground glass is similar to sand in con-sistency but may be slightly sharper to touch. Gloves can be worn while handling. No safety issues arose on site at BedZED.

Cost camparison

Recycled crushed glass sand cost £10.75/tonne from Day Aggregates. This was approximately £2/tonne cheaper than virgin material, saving the project £558 (~ 15% of the material cost). The aggregates tax implemented in April 2002 (since BedZED construction) has increased the price of virgin aggregate by a further £1.60/tonne, making potential cost savings even greater.

Quantified environmental benefits

The environmental impact of the recycled glass sand used on BedZED has been compared with virgin sand typically sourced in the UK.
recycled sand v average sand

Ecopoints 320
Embodied CO2 (kg 100 yr eq) 1,330
Embodied Energy (GJ) 17
Eco-footprint (ha years) 1

Further information

• The full report can be obtained from Bioregional: www.bioregional.com